- Existing
Development: click to view
- Received comments from first above ceiling inspection.
- Carpenter finished fire extinguisher cabinets and column covers.
- Interior glass complete with some touch up remaining.
- Porcelain floor complete, minus elevator floor area.
- Wood flooring to be complete over the weekend.
- Track flooring complete, minus final stripe layout.
- Sprinkler Inspection System Test comlete and passed.
- HVAC trim work near complete.
- Electrical general trim, fire alarm and safety work continues.
- Soccer side interior bleacher delivered and assembly started.
- Carapenter finished with all grid bordering, finished hanging doors and installing door hardward and some misc. trims.
- Interior glass is near complete.
- Porcelain floor near complete, vinyl flooring complete, wood flooring continued with paint, sports flooring complete and poured in place, flooring near complete.
- Field Turf complete.
- Elevator finished install of chair lift.
- Sprinkler trim complete and ready for inspection.
- Plumbing trim complete pending other finish work.
- HVAC thermostat trim complete pending other electrical work.
- Electricall trim continued along with fire alarm and safety work.
- Sports equipment for soccer complete and wall padding started.
- AT&T pulled main lines into building and set panel board.
- Excavator installed fines in soccer field.
- Mason complete with all work throughout.
- Carpenters continued to border grid, hang doors & accessories.
- Porcelain, vinyl and wood floors continued throughout.
- Painter near complete with all work throughout.
- Elevator is rough complete and operational.
- Plumbing trim complete, minus one or two items.
- HVAC thermostat trim work started.
- Electrical trim continued along with fire alarm and safety work.
- Excavation completed all work.
- Landscaper completed all work.
- Mason 50% complete with elevator finish work.
- Carpenter bordered grid, hung more grid, hung some doors, etc.
- Porcelain, vinyl and wood floors continued throughout.
- Painter continued with miscellaneous remaining work throughout.
- Elevator near complete and operational.
- Sprinkler trim near complete throughout.
- Plumbing trim near complete throughout.
- HVAC rough and trim near complete throughout.
- Electrical trim continued along with fire alarm and exterior lights.
- Asphalt was completed, minus markings.
- Excavation near complete with all topsoil work.
- Landscaper planted a lot of plant life throughout site area.
- Concrete worked on track discrepancy fixes.
- Iron workers finished curved roof.
- Carpenters did column box outs, grid ceiling, stud walls, etc.
- Glazers installed some more interior glass in finished frames.
- Porcelain floor near complete in all toilet/locker rooms.
- Vinyl floor continued in first floor areas.
- Marmoleum floor started and completed in basketball area.
- Wood floor started in basketball area.
- Dryfall paint completed throughout along with other miscellaneous work.
- Elevator materials arrived and work commenced.
- Sprinkler trim commenced throughout building footprint.
- Plumbing trim started and near complete throughout footprint.
- HVAC rough continued and near complete throughout footprint.
- Electrical trim near complete on 2nd floor; fire alarm work started.
- Concrete workers fixed discrepancies in concrete for wood floor installation to begin next week.
- Masons fixed bracing issue and patch work as needed.
- Iron workers near finish on curved roof and investigated leaks.
- Ornamental iron work complete, minus some misc. areas.
- Carpenters worked on poplar trim, column box outs, grids on second floor, stud walls and other misc. work.
- Drywallers mudded walls and sanded to be ready for paint.
- Flooring (porcelain) continued in first floor baths and moved to second floor baths; all is ready for plumbing trim start.
- Flooring (VCT) started on second floor and completed both large multi-purpose rooms and storage room.
- Painter worked in Rock Wall area, multi-purpose room and drywall areas as needed.
- Sprinkler near finished with all rough and trim work.
- Plumber prepped for next week trim start.
- HVAC hung socks in batting cage area, hung hard duct in multi-purpose and prepared for rock wall finish.
- Electricians have lighting on throughout 95% of the building, continue to final trim areas and move into athletic equipment power up and trim out.
- Athletic eqiupment installed all basketball area equipment, minus pads to be done at a later date, but did not finish soccer side and will need to complete afte soccer floor installation.
- Front wall sign was installed and awaits electrical connection.
- Poured in place track flooring was laid out and concrete worker has more deficiencies to correct.
- Inspection partial on Hydro Test was successful, but will need to be tested again at final.
- Excavator prepped east area for volleyball curbing and posts.
- Concrete finished all exterior remaining work.
- Iron workers near complete with curve roof, weather delayed.
- Ornamental iron workers completed interior roll gate, some additional rail work and pour stopping for track pour flooring.
- Carpenters are 95% complete with all ceiling grid work.
- Drywall workers complete with all work.
- Roofers finished all EPDM roof area fascia and trim work.
- Overhead door installers completed all overhead roiling and fire shutter doors throughout.
- Glazer is completed with all work, minus wood door glass.
- Porcelain tile started in both main level locker rooms.
- Painting completed a lot of work throughout the entire facility.
- Elevator install commenced, but was not completed as parts are on order to complete the install.
- Sprinkler setup for Hydro Test and corrected one head fitting.
- Plumber was in to correct water piping in family toilets.
- HVAC did all first floor trim and duct socks in basketball area.
- Electrical had entire first floor lighting complete, exterior parking lot poles complete, pulled power wiring throughout and started to get second floor lighting all complete.
- Athletic equipment workers installed all 14 basketball supports, boards and hoops. they began preliminary work on dividers.
- Excavator prepared remaining walk area for concrete pour.
- Concrete workers sealed concrete in required areas.
- Iron workers received curved roof panel and bent in field, but where rained out prior to install.
- Carpenters hung grid throughout 90% of first floor area.
- Drywallers rocked, mudded and sanded 95% of entire building.
- Overhead door installer installed all rolling doors and the first floor and finished more than 50 of the fire shutters on the second floor.
- Glazers finished near all the exterior glass and have completed near half the interior glass.
- Painters painted rails and ready drywall areas.
- Plumber is complete with all rough work and awaiting trim work.
- HVAC continued with trim work and rough work throughout.
- Electrical continued with lighting, pulled wire and other rough.
- Elevator was delivered and install begun.
- Floor tiling was delivered and to start Monday.
- Ornamental iron installed roof hatch ladder and misc. rails.
- Carpenters installed some doors & hardware making the building 100% lockable, but not 100% enclosed.
- Drywall is near complete and mudding and sanding near, too.
- Glazers done with all exterior framework, although awaiting re-cut pieces of glass to be complete with all exterior.
- Painting continued throughout entire building.
- Plumbers completed all rough and are awaiting trim work.
- HVAC fired up some units to get heat in the building and started with some trimand other rough throughout.
- Electricians finished RTU hook up, lighting in WDSRA space and other misc. rough work.
- Fencing modified to allow park district access to north area.
- Landscaping continued with planting of some trees on north.
- Carpenters continued with grid work on first floor, received doors, installed door hardware as needed.
- Drywall continued and near complete.
- Glazers are near complete with all exterior framework.
- Painters complete with basketball rails, second floor drywall paint and primer and other miscellaneous work.
- Plumbers near complete with all rough work throughout.
- HVAC completed duct socks in soccer area and worked on other rough throughout.
- Electricians powered up most major lighting, near complete on RTU power supply and other rough electric.
- Excavation continued with flat work and topsoil around the entire perimeter of building footprint.
- Landscaping continued and finished all sod in pond and laid out for arrival of trees.
- Concrete is near finished with all exterior flat work.- Roof curbs and hatch were installed.
- Ornamental iron continued with miscellaneous work.
- Carpenters worked on grid work throughout first floor and are near complete with it. They also hung a few more doors and installed locks and hardware on perimeter doors.
- Drywall continued along with mudding. Several rooms very near paint ready for next week.
- Glazers installed curtain wall framing and glass at stairwell and the framing for the front south face of the climbing wall.
- Painters finished all paint in batting cage area (minus drywall walls); they completed all the frames requiring glass and started to prepare for paint on basketball railings.
- Sprinkler continued with rough and is done until drop ceilings are near complete.
- Plumber continued with rough plumbing on second floor.
- HVAC hung spiral in batting cage, some in multipurpose and focused on duct socks in soccer (half complete).
- Electricians worked on main power distribution, powered up lights in soccer and basketball areas, neared power up of lights in multipurpose 2nd floor, began layout for grid lighting and other miscellaneous work.
- Rough framing, electric, plumbing, HVAC and MCP Inspections all passed, with minor fixes to occur prior to next inspection.
- Excavator started to bring top soil to prepare for future needs.
- Concrete pour/s; Remaining stoops, apron and 80% of all curbs.
- Roof copings near complete, all wall panel complete, flashings underway and near complete; railings ovelooking rock wall complete.
- Rough framing complete, drywall on single side throughout complete, insulation of all walls near complete, all exterior hollow metal doors installed (awaiting paint to finalize).
- EPDM roofing near complete, awaiting copings and flashings.
- Glass started on front rock wall area, stairwell and entry.
- Painting near complete in soccer, railings on track begun, batting cage area near ready for final coat.
- Sprinkler rough complete minus stairwells.
- Plumbing rough nearing complete; i.e., main runs, venting, etc.
- Gas piping complete to roof to RTUs; near complete to main.
- Electrical service near powered up, waiting on ComEd; all lights and fans installed in soccer area, multipurpose rough started and finished.
- Excavation of roads and walks continued and near complete.
- Concrete pour/s; basketball floor, ramps and stairs.
- Gutters and downs near finish' decking on west bump-out finished; decked ramp; set stairs and platforms; worked on high roof backer panels.
- Light gauge framing on front canopy and sheeting completed; light gauge interior framing on second floor ner complete minus bulkheads.
- Painting continued throughout with block filler and dryfall.
- Plumbing rough continued on second floor.
- HVAC rough continued on second floor.
- Electrical rough continued throughout and on main power.
- Excavation of road and walks began mid week.
- Concrete laid out for pour/s; stopps, basketball floor, etc.
- Exterior sheet metal nearly finished on all lbump-outs; gutters and downspouts started; railings on running track installed awaiting final detailing.
- Interior light gauge framing continued and is near complete.
- Kalwall installation complete (except panels left out for access).
- Painting continued throughout entire building area.
- Plumbing rough continued with focus on hose bigs and 2nd floor.
- Electrical rough continued with a focus on main power hook-up.
- Caulking started and neared completion throughout the entire building; joints, windows, frames, etc.
- Concrete pour/s; locker bases in both locker rooms.
- Masonry joint caulking completed.
- Exterior sheet metal nearing finish on bump-outs; main roof near complete (trims and flashings remain).
- Rails on running track installed and near complete; stairs delivered and prepared for installation.
- Kalwall installation continued and nearly complete.
- Painting continued throughout entire building area/s.
- Plumbing rough continued throughout entire building.
- Gas piping layout confirmed, piping to be delivered next week.
- HVAC rough continued throughout building.
- Electrical rough throughout building and site lighting pulls (wire).
- Concrete pour; remaining precast plank topping.
- Masonry is complete; sealing and caulking has begun.
- Exterior sheet metal continued and only bump-out sheet metal remains; roof nears finalization and other miscellaneous details where completed.
- Carpenters near completion with exterior framing on sheeting.
- Kalwall installation continued throughout; near complete.
- Painter continued in basketball area with structural downs, underside of running track; and began masonry block filler in basketball area and first floor main core; and started ceiling dry-fall in soccer area.
- HVAC rough continued with a focus on second floor.
- Electrical rough continued; nearing main power finalization.
- Excavation of stone in soccer building completed.
- Concrete pours, stairs, soccer and storage building areas.
- Mason continued in main core and is near completion.
- Exterior sheet metal continued; as well as rail installation, roof finalization and other miscellaneous details.
- Carpenters continued with exterior framing and sheeting.
- Kalwall installation continued throughout.
- Painter continued in basketball area, ceiling near complete.
- HVAC rough continued throughout second floor.
- Electrical rough continued throughout.
- Excavation for stone in soccer field began.
- Concrete footings and foundations poured at west wall.
- Mason finished all second floor masonry and continued with remaining first floor main core masonry.
- Exterior sheet metal commenced on north wall (north wall near finished); as well as roof crickets and other misc. details.
- Carpenters continued with exterior framing and sheeting.
- Kalwall installation began throughout.
- Painter continued in basketball area.
- Sprinkler rough continued and is near completion; riser as well.
- Plumbing continued on first floor main core.
- RTUs were set on roof and HVAC rough continued (One RTU to be set at a later date).
- Electrical rough continued throughout.
- Excavation commenced as top soil was spread in detention pond and stairwell digging for footings commenced.
- Masonry on interior second floor is near complete. Washing of all exterior masonry and foam insulation is near complete, too.
- Purlins for RTUs were modified and the roof crickets were started as well as the screen wall sheeting.
- Carpenters continued with light gauge exterior framing and sheeting of dens glass as well as interior framing at stairwell.
- Painting continued on ceiling in basketball area.
- Sprinkler rough continued in soccer area and is near complete; sprinkler riser rough started.
- Plumbing continued on first floor and passed several inspections.
- Mechanical (HVAC) rough continued throughout; roof exhaust fans were installed, fire dampers at batting cage transition installed and drops for RTUs installed.
- Electrical rough continued throughout entire building area.
- Masonry neared finalization on exterior and interior first floor main core layout went well.
- Iron workers installed all but one remaining roof curbs and did some touch up (detailing) work throughout the building.
- Sheet metal workers installed parapet backing and started screen wall secondary framing.
- Carpenters mobilized and started both interior and exterior light gauge walls (more focused on interior 2nd floor).
- Sprinkler rough continued throughout and is nearing completion.
- Plumber rough continued behind mason on 1st floor main core.
- Mechanical rough continued throughout and preparation for unit delivery commenced.
- Electrical rough continued throughout, with a focus on gearing.
- Concrete was poured at north stairs and elevator pump room.
- Masonry was scattered by weather; only minimal exterior work was completed (entrance, etc.) while interior 2nd floor work is near completion.
- Sheet metal work was minimal on north parapet due to weather.
- Carpenters set more door and window frames as needed.
- Sprinkler rough continued throughout and is nearing completion.
- Plumbing rough continued on second floor behind masonry.
- Mechanical rough continued throughout building.
- Electrical rough continued with a focus on gearing, which is nearly complete.
- Masonry commenced on the exterior with a focus on the main entry. Interior work was also performed on 2nd floor walls on 8 and 10 lines.
- Carpenters set door and window frames throughout.
- Sprinkler rough continued throughout the main core 1st and 2nd floor areas.
- Plumbing rough continued throughout the main core on 1st floor, focusing on sanitary runs with minor work on domestic water.
- Mechanical (HVAC) rough continued throughout the main core on 1st and 2nd floors.
- Electrical rough continued throughout the building. Runs for exterior site lighting began and neared finalization.
- Sheet metal began on north wall with all vertical panel being completed and a start on the decorative band and horizontal panel.
- Rock climbing wall installation was completed (further detailing required at later date).
- Masonry walls at the climbing wall area are near complete.
- Masons have begun to box out interior columns in the batting cage area.
- Masons are about 75% complete with elevator shaft.
- Under slab plumbing in the main core area is complete and backfilled. Final grading is complete and ready for concrete.
- Sprinkler rough continues on both levels.
- Stems for high bay lighting in soccer and basketball areas are complete.
- Electrical rough continues in slab areas where concrete will be poured in the coming days.
- Com Ed transformer is set.
- Started hanging main duct runs on second floor.
- North end of basketball gym is graded.
- Excavator stoned interior room 113 (rock wall).
- Concrete was poured on remaining running track decking and in room 113 (rock wall).
- Masonry commenced on exterior with a main focus on the building corners and at the main entry/rock wall.
- Steel at rock wall was finalized only to a point to allow for later date rock wall delivery.
- Sprinkler pipe install continued throughout building.
- Plumber near finalized with under slab.
- Mechanical contractor mobilized on site and began with 2nd floor layouts.
- Electrician continued with rough and started core and runs for main power feed to the power.
- Torque tested Phase 2 steel and passed.
- Concrete was poured on 75% of interior running track and on deck in rooms 202, 204, 206-212, 215 and 217.
- Received final precast floor plank delivery, set, grouted and barred cores to masonry as required.
- Masonry continued throughout the interior as needed and on the exterior perimeter.
- Started to set steel at room 103 and continued with roof curbs.
- Received remaining H.M. frames and set ones required.
- Sprinkler piping began in phase 2 building.
- Under slab plumbing began in main core and is near complete.
- Electrical rough in building continues and layout/planning for main power feed started.
- Landscapers are near 95% complete with detention pond retaining wall, including drainage, backfill and block/pavers.
- Excavator stoned interior rooms in north quadrant of building.
- Interior concrete slabs were poured in rooms 113, 133, 134, 135, 136 and 139 (batting cage, hall, storage, mech. and stairwells).
- Interior running track was prepped for concrete pour for Monday.
- Interior masonry walls were constructed throughout the southern portion of the building for rooms 105, 106, 107, 109, 111 and 113 (mechanical, sprinkler, storages, hall and batting cage).
- Exterior masonry walls continued to be constructed on all sides.
- Hollow metal frames delivered and necessary frames were set.
- Steel frame on H line set as was as detailing on south face of building, finalizing metal decking and window unit frame setting.
- Electrical rough continued in all areas and underslabs.
- Interior masonry work was completed as needed for precast installation.
- Received second series of precast, but was unable to set the entire shipment due to a break in the plank.
- Electrical rough continued through the entire building.
- Temporary power was brought to the building and temporary lighting is in.
- Started detention pond retaining wall (block wall).
- Started roof screening framing work.
- Minor entry road work was completed this week to help with site drainage during rainy weather.
- The detention pond was cut and prepped for the soon to be installed retaining wall.
- The detention pond storm lines where final connected to the main village storm system.
- Interior masonry walls continued to be completed in areas needed for precast installation and other areas as well.
- Exterior masonry installation commenced along the entire north side of the building and down a portion of the east side of the building.
- Electrical rough continued throughout the entire building area.
- The first series of precast floor planks were delivered and installed.
- Steel decking went down on a majority of the running track.
- Finalized erecting of Phase 2 steel, minus the areas required to be left for later precast installation.
- Detailing of Phase 2 steel is near 70% complete.
- Installation of Elevated Track Steel started - 5% complete.
- Interior masonry footing excavation is near 60% complete,
- Inspection on Sanitary Service (pressure test) passed.
- Mason has begun to mobilize on site with equipment.
- Backfilling (spoils) and slight grading (to help with site drainage) of site around perimeter.
- Received most of the remaining steel building materials. More deliveries next week.
- Continued erection of Phase 2 steel building - approximately 60% complete.
- Roof on soccer building portion complete with detailing to commence further in the schedule.
- Electricians started to rough in conduit in the soccer building - completed almost three full bays of runs.
- Excavation of interior masonry footings began Friday. Frost still remains in the ground to approximately 20" below subgrade.
-Concrete foundations completed between 2 and 10, between G and M (entire elevator, rockwall and entrance areas).
- Concrete piers and footings completed for interior application along line 8.
- Excavation of interior piers along 6 and 8 line.
- Excavation of foundation walls along 1 line between D and G, including stairwell building bump out.
- Backfill of stone and soils on line 1 between A and D.
- Access drive to site relocated and stiffened for construction traffic continuation.
- Steel building (soccer portion only) completely set and detailed out.
- Steel roofing and insulation laid out for next week install.
-
Framed interior piers at column line 10.
- Framed north and south foundation walls westward past column line 10 approximately 5' 10".
- Insulated foundation walls on south, east and north walls, minus areas of current framing an concrete pouring.
- Back filled interior (stone) and exterior (spoils stone where required) foundation walls on south, east and north walls, minus areas of current framing and concrete pouring.
- Installed setting plates in 1" grout on south, east and north completed piers.
- Poured concrete at pier and wall locations on column line 10.
- Footing trenches were covered with reinforced plastic and concrete blankets and the trench was heated for several days in order to remove all frost from the trench.
- Footing was poured on Wednesday and covered.
- Layout of foundation walls has begun and will continue into next week.
- The pad has been built and the lot rough graded. Parking lot and driveway have begun to take shape. The construction entrances have also been installed.
- the detention area has mostly been cut to grade and will be finished once the weather allows.
- The building, storm and sanitary systems have been laid out.
- The sanitary connection has been made and brought through the existing parking lot as well. The first structure has been set.
- Work on the temporary power has begun with placing conduit and setting the transformer that is needed.
- View full history
Prior to the November 7, 2006 election, the park district conducted a series of open houses to explain the referendum and gather public input. The meetings were promoted at park board meetings, on the park district's Website, in eblasts and newspaper advertisements.
The park district mailed to every home a tri-fold brochure that explained the referendum, listed the open houses and invited residents to them. In addition, a series of postcards, highlighting the referendum's three key components, encouraging residents to contact the park district for more information were distributed throughout the community.
Complete detailed information regarding the referendum, including its three key components and financial information, was available at the open houses, and in binders at the front desks of Main Street Recreation Center and Spring Avenue Recreation Center. The same information was posted on the park district's Website where residents could view, download and print the information. Click to view the following information:
The complex addresses the needs of record growth in recreational sports and shortage of indoor space and gymnasiums. The new neighborhood facility will include a large, indoor multi-purpose field with special turf, three basketball courts with wood floors, a climbing wall, walking/running/jogging track and is designed for:
- Badminton
- Baseball
- Field Hockey
- Football
- Lacrosse
- Rugby
- Soccer
- Softball
- Volleyball
In addition to serving the greatest number of people by being multi-purpose, this facility will give our youth an advantage by allowing them to play and practice their sport year 'round. It will allow local schools more access to their own gymnasiums. It will also provide for relief parents who will no longer have to drive their kids to Aurora, southern Naperville or Orland Park to use an indoor sports facility.
- View Ackerman Park Sports Complex - 1st floor
- View Ackerman Park Sports Complex - 2nd floor
- View Ackerman Park Sports Complex rendering
|